Skip to content
Deedo home
Menu

Hum Developers Private Limited

Company or firm · 10 projects · 10 MahaRERA registrations

10Projects10 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Siddharth Avenue C WingP99000015995Palghar2018Not reported30 Mar 2022—On date
Vishal-1P51800045937Borivali2022Certificate Signed31 Mar 202531 Mar 2025On date
Hum SolarisP51800053518Charkop2023Not reported31 Dec 2026—On date
GagansagarP51800055645Borivali2024Certificate Signed31 Dec 202630 Apr 2027+4 months
Hum DurgaP51800056010Dahisar2024Not reported31 Dec 2026—On date
Hum GS HeightsPM1180002502424Kandivali2026Not reported31 Dec 2031—On date
Hum Emerald HeightsPM1180002502952Charkop2026Certificate Signed31 Dec 202930 Apr 2030+4 months
Hum Galaxy HeightsPM1180002600762Charkop2026Not reported31 Dec 2030—On date
Hum SapphirePM1180002601373Borivali2026Not reported31 Dec 2030—On date
Hum LaxmiPR1180002601424Dahisar2026Not reported31 Dec 2030—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Siddharth Avenue C WingOn date
  • Vishal-1On date
  • Hum SolarisOn date
  • Gagansagar+4 mo
  • Hum DurgaOn date
  • Hum GS HeightsOn date
  • Hum Emerald Heights+4 mo
  • Hum Galaxy HeightsOn date
  • Hum SapphireOn date
  • Hum LaxmiOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Gagansagar (P51800055645).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology