Hubtown Limited
Company or firm · 7 projects · 8 MahaRERA registrations
7Projects8 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date4 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Hubtown SolarisP51800001465 | Andheri | 2017 | Not reported | 30 Dec 2022 | — | On date |
| Hubtown Premiere Residences - BeverlyP51800002671 | Andheri | 2017 | Not reported | 31 Jul 2029 | — | On date |
| Hubtown Premiere ResidencesP51800002977 | Andheri | 2017 | Not reported | 31 Jul 2029 | — | On date |
| Hubtown Premiere Residences - CommercialP51800003575 | Andheri | 2017 | Not reported | 31 Jul 2026 | — | On date |
| Hubtown Premiere Residences - MalibuP51800005224 | Andheri | 2017 | Not reported | 31 Jul 2029 | — | On date |
| Hubtown Premiere Residences - Bel AirP51800005688 | Andheri | 2017 | Not reported | 31 Jul 2026 | — | On date |
| Hubtown Premiere ResidencesP51800006839 | Andheri | 2017 | Not reported | 31 Jul 2029 | — | On date |
| Solaris 14th FloorP51800028276 | Andheri | 2021 | Not reported | 30 Jun 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology