Hezal Construction
Company or firm · 5 projects · 5 MahaRERA registrations
Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date80%4 of 5 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sai SangatP52000021890 | Ulawe | 2019 | Not reported | 30 Mar 2022 | 30 Mar 2023 | +12 months |
| Om Shiv SaiP52000024729 | Wahal | 2020 | Not reported | 30 Dec 2023 | — | On date |
| Om Shiv SureshP52000025603 | Wahal | 2020 | Not reported | 30 Jun 2023 | — | On date |
| Sai Guru ResidencyP52000027093 | Wahal | 2020 | Not reported | 30 Jun 2023 | — | On date |
| Hezal OrchidP52000028415 | Wahal | 2021 | Not reported | 30 Sep 2023 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Sai Sangat (P52000021890).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology