Company or firm · first RERA registration 2017

Harihar Infrastructure Development Corporation Limited

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 92 mo late — longer than Maharashtra's 4 mo.

Projects45 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay92 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 5 ran past the RERA date

Months late against the original RERA promise, per registration

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Harihar Nagar ZariP50500000975Nagpur (Rural)Certificate Signed2 Sep 20332 Sep 2033On date
Gokulpark Tower No 1P50500006428Nagpur (M Corp.)Active31 Dec 201831 Dec 2033+180 mo
Gokulpark IIP50500048220Nagpur (M Corp.)Certificate Signed31 Dec 202531 Dec 2025On date
Harihar Nagar ZariP50500077264Nagpur (Rural)Certificate Signed31 Dec 203431 Dec 2034On date
Harihar Nagar Zari Phase II Building No. 4 & 5PR1190002502559ZariCertificate Signed31 Dec 203530 Apr 2036+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology