RegisteredExtendedMahaRERA status: Certificate Signed

PR1190002502559

Harihar Nagar Zari Phase II Building No. 4 & 5 · Zari, Nagpur · Harihar Infrastructure Development Corporation Limited

Promised for 31 Dec 2035, extended to 30 Apr 2036, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2035 to 30 Apr 2036.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate2 Mar 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about PR1190002502559

Is Harihar Nagar Zari Phase II Building No. 4 & 5 delayed?

Its completion moved from 31 Dec 2035 to 30 Apr 2036; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for PR1190002502559. The completion date moved from 31 Dec 2035 to 30 Apr 2036.

Who is the promoter?

MahaRERA records Harihar Infrastructure Development Corporation Limited as the promoter of PR1190002502559.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names PR1190002502559.

Answers are generated from the record.

Data through25 Oct 2026, 03:29SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology