Company or firm · first RERA registration 2019

Happy Home Corporation

Deedo IDDD-BGB5

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 2 mo late.

Projects23 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay2 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Happy Home Lily KunjP51800019214AndheriCertificate Signed30 Oct 202130 Oct 2021On date
Happy Home JasmineP99000048250Vasai Virar City (M Corp)Certificate Signed31 Mar 202831 Mar 2028On date
Happy Home JasmineP99000048251Vasai Virar City (M Corp)Certificate Signed30 Sep 202630 Sep 2026+2 mo*

Happy Home Corporation, in questions

Does Happy Home Corporation finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 2 mo late. Across Maharashtra, 73% kept their date.

How many projects has Happy Home Corporation registered with MahaRERA?

2 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.

Does Happy Home Corporation have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.