Guardian Homes Private Limited

Company or firm · 2 projects · 3 MahaRERA registrations

Projects23 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Guardian CityscapesP52100003214Parvati2017Not reported30 Jun 2024—On date
Guardian CityscapesP52100003427Parvati2017Not reported29 Jun 202430 Jun 2025+12 months
Guardian Cityscapes Phase-3P52100028630Parvati2021Not reported30 Jun 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Guardian CityscapesOn date
  • Guardian Cityscapes+12 mo
  • Guardian Cityscapes Phase-3On date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Guardian Cityscapes (P52100003427).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology