Guardian Homes Private Limited
Company or firm · 2 projects · 3 MahaRERA registrations
Projects23 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Guardian CityscapesP52100003214 | Parvati | 2017 | Not reported | 30 Jun 2024 | — | On date |
| Guardian CityscapesP52100003427 | Parvati | 2017 | Not reported | 29 Jun 2024 | 30 Jun 2025 | +12 months |
| Guardian Cityscapes Phase-3P52100028630 | Parvati | 2021 | Not reported | 30 Jun 2027 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 12 months, for Guardian Cityscapes (P52100003427).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.