Green Lifespaces
Deedo IDDD-5J01Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 62 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Green Willows Phase IP51700012824 | Shendrun Bk. | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | +59 mo* |
| Green Willows Phase IIP51700012825 | Shendrun Bk. | Certificate Signed | 30 Jun 2021 | 30 Jun 2021 | +65 mo* |
Green Lifespaces, in questions
Does Green Lifespaces finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 62 mo late. Across Maharashtra, 73% kept their date.
How many projects has Green Lifespaces registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Green Lifespaces have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.