Company or firm · first RERA registration 2018

Gokhale Realty Llp

Deedo IDDD-31PV

Of 4 registrations whose promised date has arrived, 1 kept it (25%). The rest ran a median 29 mo late.

Projects44 RERA registrations
Kept RERA date25%Maharashtra: 73%
Median delay29 mowhen late
First sales on record44registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
KrishnanayanP52100016898Pune (M Corp.)Certificate Signed30 Dec 202130 Dec 2021On date
ChintamanishreeP52100026885KothrudCertificate Signed30 Jun 202430 Jun 2024+29 mo*
KojagiriP52100027400KothrudCertificate Signed30 Jun 202430 Jun 2024+29 mo*
Anuprita BP52100028122KothrudCertificate Signed30 Jun 202530 Jun 2025+17 mo*

Gokhale Realty Llp, in questions

Does Gokhale Realty Llp finish projects on time?

Of 4 MahaRERA registrations whose promised completion date has arrived, 1 kept it (25%). The rest ran a median 29 mo late. Across Maharashtra, 73% kept their date.

How many projects has Gokhale Realty Llp registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.

Does Gokhale Realty Llp have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology