Gokhale Constructions
Deedo IDDD-Y7CEOf 14 registrations whose promised date has arrived, 5 kept it (36%). The rest ran a median 12 mo late.
Delivery record
13 of 18 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 18 registrations
18 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| SaloniP52100003071 | Erandwana | Certificate Signed | 31 Jan 2018 | 31 Dec 2019 | +23 mo |
| WavesP52100003292 | Wakad | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Saraswati ParkP52100004346 | Kothrud | Certificate Signed | 31 Jan 2020 | 30 Jan 2022 | +24 mo |
| VandanshreeP52100005003 | Kothrud | Certificate Signed | 31 Dec 2018 | 30 Dec 2019 | +12 mo |
| Pooja RajasP52100013970 | Kothrud | Certificate Signed | 30 Sep 2019 | 30 Oct 2020 | +13 mo |
| Sulabh MonaliP52100014571 | Pune (M Corp.) | Certificate Signed | 30 Nov 2019 | 30 Nov 2020 | +12 mo |
| Shashi MadhavP52100015131 | Bavdhan Khurd | Certificate Signed | 31 Dec 2019 | 31 Jan 2021 | +13 mo |
| ShraddhaP52100016406 | Pune (M Corp.) | Certificate Signed | 28 Feb 2021 | 28 Feb 2021 | On date |
| SwastishreeP52100017399 | Aundh | Certificate Signed | 30 Sep 2020 | 30 Sep 2020 | On date |
| ZelamP52100020973 | Erandwana | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| ManikP52100023658 | Erandwana | Certificate Signed | 30 Mar 2023 | 30 Mar 2023 | On date |
| PushpakunjP52100023681 | Kothrud | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | +35 mo* |
| AyodhyanagarP52100032277 | Kothrud | Certificate Signed | 31 Oct 2026 | 31 Oct 2026 | +1 mo* |
| Ganga Lahari Co-Operative Housing Society LtdP52100051998 | Karve Nagar | Certificate Signed | 31 Oct 2026 | 31 Oct 2026 | +1 mo* |
| Shree Ganesh Avantika ChslP52100054787 | Kothrud | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
| UmaPR1260002501285 | Parvati | Certificate Signed | 30 Jun 2028 | 30 Oct 2028 | +4 mo |
| ManodeepPR1260002600823 | Kothrud-Ext | Certificate Signed | 1 May 2029 | 1 Sep 2029 | +4 mo |
| Shree Ganesh Park ChslPR1260002601231 | Kothrud | Certificate Signed | 30 Jun 2031 | 30 Oct 2031 | +4 mo |
Show all 18 registrationsShow fewer
Gokhale Constructions, in questions
Does Gokhale Constructions finish projects on time?
Of 14 MahaRERA registrations whose promised completion date has arrived, 5 kept it (36%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.
How many projects has Gokhale Constructions registered with MahaRERA?
18 projects under 18 MahaRERA registrations; 11 completed on MahaRERA.
Does Gokhale Constructions have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.