Gayasuddin Riyazuddin Khan
Deedo IDDD-9V0GOf 4 registrations whose promised date has arrived, 3 kept it (75%). The rest ran a median 4 mo late.
Delivery record
4 of 7 registrations with dates moved or missed their RERA date · months late against the original promise
7 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mountain ValleyP51700009583 | Mumbra | Certificate Signed | 30 Oct 2020 | 30 Oct 2020 | On date |
| Universe I Phase IP51700009797 | Thane (M Corp.) | Completed | 30 Dec 2023 | — | On date |
| The Heavens PalaceP51700020942 | Shil | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Rose NagarP51700030263 | Mumbra | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | +29 mo* |
| The Universe Neptune - BP51700049457 | Kausa | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| The Heavens PalaceP51700077717 | Shil | Certificate Signed | 1 Dec 2027 | 1 Apr 2028 | +4 mo |
| The Heavens PalaceP51700078962 | Shil | Certificate Signed | 1 Dec 2027 | 1 Apr 2028 | +4 mo |
Gayasuddin Riyazuddin Khan, in questions
Does Gayasuddin Riyazuddin Khan finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 3 kept it (75%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Gayasuddin Riyazuddin Khan registered with MahaRERA?
6 projects under 7 MahaRERA registrations; 3 completed on MahaRERA.
Does Gayasuddin Riyazuddin Khan have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.