Deedo IDDD-HMMROf 5 registrations whose promised date has arrived, 2 kept it (40%). The rest ran a median 20 mo late.
Delivery record
5 of 10 registrations with dates moved or missed their RERA date · months late against the original promise
10 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Gods CountyP52100005522 | Charholi Kh | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Gods CountyP52100006336 | Charholi Kh | Certificate Signed | 31 Dec 2020 | 31 Dec 2024 | +71 mo* |
| Ganesh SamruddhiP52100019912 | Dapodi | Certificate Signed | 30 Oct 2022 | 30 Oct 2022 | +49 mo* |
| Ganesh EliteP52100021213 | Dapodi | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Ganesh Siddhi B1 B2P52100029881 | Chikhali | Certificate Signed | 31 Mar 2025 | 31 Mar 2025 | +20 mo* |
| Ganesh Siddhi Wing DP52100029882 | Chikhali | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Ganesh Siddhi E WingP52100031103 | Chikhali | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Ganesh Siddhi C1 C2P52100051914 | Chikhali | Certificate Signed | 31 Mar 2025 | 31 Mar 2025 | On date |
| Ganesh Siddhi Phase 4P52100080123 | Chikhali | Active | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Ganesh Siddhi Phase 5P52100080668 | Chikhali | Active | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
Ganeshconstruction, in questions
Does Ganeshconstruction finish projects on time?
Of 5 MahaRERA registrations whose promised completion date has arrived, 2 kept it (40%). The rest ran a median 20 mo late. Across Maharashtra, 73% kept their date.
How many projects has Ganeshconstruction registered with MahaRERA?
9 projects under 10 MahaRERA registrations; 2 completed on MahaRERA.
Does Ganeshconstruction have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.