Ganesh Chandrakant Malvankar
Deedo IDDD-01ZBOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 17 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Broadway AnnexP51700026672 | Naupada | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | +29 mo* |
| New Suyash CHSP51700052617 | Naupada | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
Ganesh Chandrakant Malvankar, in questions
Does Ganesh Chandrakant Malvankar finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 17 mo late. Across Maharashtra, 73% kept their date.
How many projects has Ganesh Chandrakant Malvankar registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Ganesh Chandrakant Malvankar have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.