Gandharv Developers
Deedo IDDD-3VAYOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 5 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Gandharv SerenityP52100005405 | Hadapsar | Certificate Signed | 30 Jun 2019 | 31 Dec 2019 | +6 mo |
| Gandharv LeelaPM1260002600844 | Hadapsar | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
Gandharv Developers, in questions
Does Gandharv Developers finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 5 mo late. Across Maharashtra, 73% kept their date.
How many projects has Gandharv Developers registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Gandharv Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.