Gajanan Shyamrao Khabale
Deedo IDDD-M917Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 37 mo late.
Delivery record
2 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shivani HeritageP51700008458 | Navi Mumbai (M Corp.) | Certificate Signed | 31 Mar 2019 | 30 Sep 2020 | +18 mo |
| Jai Malhar ApartmentP52000018661 | Shedung | Certificate Signed | 30 Mar 2022 | 30 Mar 2022 | +56 mo* |
| Jai Malhar Apartment Phase - IP52000048891 | Shedung | Certificate Signed | 30 Nov 2024 | 30 Nov 2024 | On date |
| Jai Malhar Apartment Phase IIP52000050795 | Shedung | Certificate Signed | 31 Dec 2026 | 31 Dec 2025 | On date |
| Jai Malhar Apartment Phase - VPR1270002601648 | Shedung | Certificate Signed | 31 Mar 2029 | 31 Mar 2029 | On date |
Gajanan Shyamrao Khabale, in questions
Does Gajanan Shyamrao Khabale finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 37 mo late. Across Maharashtra, 73% kept their date.
How many projects has Gajanan Shyamrao Khabale registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 2 completed on MahaRERA.
Does Gajanan Shyamrao Khabale have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.