Gagangiri Construction

Company or firm · 5 projects · 5 MahaRERA registrations

Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
AerovistaP51800012150Andheri2017Not reported30 Dec 202328 Dec 2025+24 months
Gagan 138P51800033983Kurla2022Not reported31 Dec 2025—On date
AadhyaP51800079135Kandivali2025Not reported31 Dec 2029—On date
The ElevatePM1180002600570Charkop2026Not reported10 Apr 2031—On date
Gagan 52PM1180002600783Kurla2026Not reported30 Apr 2031—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Aerovista+24 mo
  • Gagan 138On date
  • AadhyaOn date
  • The ElevateOn date
  • Gagan 52On date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 24 months, for Aerovista (P51800012150).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology