Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late.

Projects55 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

4 of 5 registrations with dates moved or missed their RERA date · months late against the original promise

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
AerovistaP51800012150AndheriCertificate Signed30 Dec 202328 Dec 2025+35 mo*
Gagan 138P51800033983KurlaCertificate Signed31 Dec 202531 Dec 2025On date
AadhyaP51800079135KandivaliCertificate Signed31 Dec 202930 Apr 2030+4 mo
The ElevatePM1180002600570CharkopCertificate Signed10 Apr 203110 Aug 2031+4 mo
Gagan 52PM1180002600783KurlaCertificate Signed30 Apr 203130 Aug 2031+4 mo

Gagangiri Construction, in questions

Does Gagangiri Construction finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Gagangiri Construction registered with MahaRERA?

5 projects under 5 MahaRERA registrations; 1 completed on MahaRERA.

Does Gagangiri Construction have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.