Gagangiri Construction
Company or firm · 5 projects · 5 MahaRERA registrations
Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| AerovistaP51800012150 | Andheri | 2017 | Not reported | 30 Dec 2023 | 28 Dec 2025 | +24 months |
| Gagan 138P51800033983 | Kurla | 2022 | Not reported | 31 Dec 2025 | — | On date |
| AadhyaP51800079135 | Kandivali | 2025 | Not reported | 31 Dec 2029 | — | On date |
| The ElevatePM1180002600570 | Charkop | 2026 | Not reported | 10 Apr 2031 | — | On date |
| Gagan 52PM1180002600783 | Kurla | 2026 | Not reported | 30 Apr 2031 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 24 months, for Aerovista (P51800012150).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology