Company or firm · first RERA registration 2019

Future Buildcon

Deedo IDDD-7PNT

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late.

Projects44 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Future ExoticaP52000021000Motha KhandaCertificate Signed30 Mar 202330 Mar 2023On date
Future LandmarkP52000052573New PanvelCertificate Signed31 May 202630 Sep 2026+6 mo*
Future CornerPR1270002500306AkurliCertificate Signed31 Mar 203031 Jul 2030+4 mo
Future AmrutPR1270002500949Wangani Tarf WajeCertificate Signed30 Jun 202730 Oct 2027+4 mo

Future Buildcon, in questions

Does Future Buildcon finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Future Buildcon registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.

Does Future Buildcon have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.