Deedo IDDD-MK5JOf 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 4 mo late.
Delivery record
7 of 11 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 11 registrations
11 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Fortune HouseP52100005111 | Pune (M Corp.) | Certificate Signed | 31 Oct 2018 | 31 Oct 2018 | On date |
| Vishwambhar Co-Operative Housing Society LimitedP52100048856 | Kothrud | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| State Bank Of India Employees Himgauri Co Operative Housing Society LtdP52100050860 | Pune City | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 mo |
| Garud House Apartment CondominiumP52100050895 | Pune (M Corp.) | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| MadhvachhayaP52100053769 | Pune (M Corp.) | Certificate Signed | 16 Jun 2025 | 16 Jun 2025 | On date |
| Abhishek Co Operative Housing Society LimitedP52100053895 | Shivajinagar Bhamburda | Certificate Signed | 5 Jun 2026 | 5 Jun 2026 | +5 mo* |
| Prashanti Co Operative Housing Society LimitedP52100066493 | Pune (M Corp.) | Certificate Signed | 15 Mar 2027 | 15 Jul 2027 | +4 mo |
| Yashodhan Co-Operative Housing SocietyPM1260002400079 | Pune (M Corp.) | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 mo |
| Kusum Co. Operative Housing Society LimitedP52100077837 | Shivajinagar Bhamburda | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 mo |
| SaikrupaP52100080508 | Erandwana | Certificate Signed | 25 Jun 2028 | 25 Oct 2028 | +4 mo |
| Fortune SakarPR1260002600591 | Erandwana North | Certificate Signed | 20 Mar 2029 | 20 Jul 2029 | +4 mo |
Show all 11 registrationsShow fewer
Fortune Developers, in questions
Does Fortune Developers finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 2 kept it (50%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Fortune Developers registered with MahaRERA?
11 projects under 11 MahaRERA registrations; 3 completed on MahaRERA.
Does Fortune Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.