Fine Homes
Deedo IDDD-PF1WOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 20 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Pride ApartmentP99000025508 | Makane | Certificate Signed | 30 Nov 2023 | 30 Nov 2023 | +36 mo* |
| Park - 16P99000034593 | Makane | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
Fine Homes, in questions
Does Fine Homes finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 20 mo late. Across Maharashtra, 73% kept their date.
How many projects has Fine Homes registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Fine Homes have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.