Dynamic Realty Enterprises
Deedo IDDD-JFRZOf 2 registrations whose promised date has arrived, 2 kept it (100%).
Delivery record
None of 3 registrations with dates has moved or missed its RERA date
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Dynamic GrandeurP52100001831 | Undri | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Dynamic GrandeurP52100005396 | Undri | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Dynamic Grandeur PremiumP52100015682 | Undri | Completed | 30 Dec 2026 | 30 Dec 2026 | On date |
Dynamic Realty Enterprises, in questions
Does Dynamic Realty Enterprises finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Dynamic Realty Enterprises registered with MahaRERA?
2 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.
Does Dynamic Realty Enterprises have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.