Company or firm · first RERA registration 2017

Dynamic Realty Enterprises

Deedo IDDD-JFRZ

Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects23 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
First sales on record3registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 3 registrations with dates has moved or missed its RERA date

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Dynamic GrandeurP52100001831UndriCertificate Signed30 Dec 202230 Dec 2022On date
Dynamic GrandeurP52100005396UndriCertificate Signed30 Jun 202430 Jun 2024On date
Dynamic Grandeur PremiumP52100015682UndriCompleted30 Dec 202630 Dec 2026On date

Dynamic Realty Enterprises, in questions

Does Dynamic Realty Enterprises finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Dynamic Realty Enterprises registered with MahaRERA?

2 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.

Does Dynamic Realty Enterprises have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology