Durvankur Vastunirmiti Private Limited
Deedo IDDD-J6DHOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 8 mo late.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Durvankur SrushtiP52100010911 | Narhe | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Durvankur SrushtiP52100047389 | Narhe | Lapsed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
| RugvedPR1300002501877 | Satara | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
Durvankur Vastunirmiti Private Limited, in questions
Does Durvankur Vastunirmiti Private Limited finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has Durvankur Vastunirmiti Private Limited registered with MahaRERA?
2 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does Durvankur Vastunirmiti Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.