Dreamz Infraspace
Deedo IDDD-T7CXOf 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 21 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Dreamz ParkP50300005712 | Amravati (M Corp.) | Completed | 30 Jun 2019 | — | On date |
| Dreamz ParkP50300007239 | Amravati (M Corp.) | Certificate Signed | 30 Sep 2019 | 30 Sep 2019 | On date |
| Dreamz SignatureP50300013798 | Amravati (M Corp.) | Completed | 31 Mar 2020 | 30 Dec 2021 | +21 mo |
Dreamz Infraspace, in questions
Does Dreamz Infraspace finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 21 mo late. Across Maharashtra, 73% kept their date.
How many projects has Dreamz Infraspace registered with MahaRERA?
2 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.
Does Dreamz Infraspace have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.