Divya Associates
Deedo IDDD-9ZYBOf 5 registrations whose promised date has arrived, 2 kept it (40%). The rest ran a median 5 mo late.
Delivery record
3 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Austin PlazaP52100003698 | Wakad | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Austin VallabhP52100018994 | Haveli | Certificate Signed | 30 Mar 2022 | 30 Mar 2022 | +56 mo* |
| Austin Park NXTP52100021130 | Tathwade | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Austin OneP52100029297 | Pimpale Saudagar | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +5 mo* |
| Austin ArenaP52100031287 | Tathwade | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 mo |
Divya Associates, in questions
Does Divya Associates finish projects on time?
Of 5 MahaRERA registrations whose promised completion date has arrived, 2 kept it (40%). The rest ran a median 5 mo late. Across Maharashtra, 73% kept their date.
How many projects has Divya Associates registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 2 completed on MahaRERA.
Does Divya Associates have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.