Dinesh Mohanlal Jain

Individual promoter · 8 projects · 8 MahaRERA registrations

Projects88 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%5 of 5 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Saraswati SankulP52800005382Ratnagiri (M Cl)2017Not reported27 Jan 2020—On date
Nirmal ParadiseP52800007060Kuwarbav (Ct)2017Not reported14 Apr 2022—On date
Shashank ParadiseP52800014822Ratnagiri (M Cl)2018Not reported30 Mar 2023—On date
Khedekar SankulP52800019504Zadgaon Ct2019Not reported30 Jan 2023—On date
Nalini Vasant ViharP52800026079Zadgaon Ct2020Not reported31 Jul 2024—On date
DJ SkyLinkP52800031130Ratnagiri (M Cl)2021Not reported31 Dec 2027—On date
Rajlaxmi SankulP52800054042Rahataghar2023Not reported31 Dec 2028—On date
Shreejee Ocean ViewP52800055303Ganapatipule2024Not reported31 Mar 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Saraswati SankulOn date
  • Nirmal ParadiseOn date
  • Shashank ParadiseOn date
  • Khedekar SankulOn date
  • Nalini Vasant ViharOn date
  • DJ SkyLinkOn date
  • Rajlaxmi SankulOn date
  • Shreejee Ocean ViewOn date

Track record notes

  • 5 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology