Individual promoter · first RERA registration 2017

Darshan Kirtikumar Bafna

Deedo IDDD-QATG

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 6 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay6 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
OrionP52000000270Pen (M Cl)Certificate Signed30 Sep 202030 Sep 2020On date
Orion PlusP52000026308PenCertificate Signed30 Sep 202331 Mar 2024+6 mo

Darshan Kirtikumar Bafna, in questions

Does Darshan Kirtikumar Bafna finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 6 mo late. Across Maharashtra, 73% kept their date.

How many projects has Darshan Kirtikumar Bafna registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.

Does Darshan Kirtikumar Bafna have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology