D. S. Kulkarni Developers Limited

Deedo IDDD-RGH8

Of 6 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 73 mo late.

Projects66 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay73 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases6includes insolvency

Delivery record

6 of 6 registrations with dates moved or missed their RERA date · months late against the original promise

6 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
Listed as an NCLT insolvency projectDsk MadhukoshListed as NCLT project: DSK MADHUKOSHNot on record
Listed as an NCLT insolvency projectDsk Gold LeafListed as NCLT project: DSK GOLD LEAFNot on record
Listed as an NCLT insolvency projectDsk MayurbanListed as NCLT project: DSK MAYURBANNot on record
Listed as an NCLT insolvency projectDsk NandanvanListed as NCLT project: DSK NANDANVANNot on record
Listed as an NCLT insolvency projectDsk AnandghanListed as NCLT project: DSK ANANDGHANNot on record
Listed as an NCLT insolvency projectWaterfall ResidenceListed as NCLT project: WATERFALL RESIDENCENot on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Dsk Gold LeafP52100004230BanerCertificate Signed30 Oct 202030 Oct 2020+73 mo*
Dsk MayurbanP52100004304PirangutCertificate Signed30 Oct 202030 Oct 2020+73 mo*
Dsk AnandghanP52100005158DhayariCertificate Signed30 Apr 202230 Apr 2022+55 mo*
Dsk NandanvanP52100005572PirangutCertificate Signed30 Oct 202030 Oct 2020+73 mo*
Waterfall ResidenceP52100007164HaveliCertificate Signed30 Oct 202230 Oct 2022+49 mo*
Dsk MadhukoshP51800009465KurlaCertificate Signed30 Apr 201930 Apr 2019+91 mo*

D. S. Kulkarni Developers Limited, in questions

Does D. S. Kulkarni Developers Limited finish projects on time?

Of 6 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 73 mo late. Across Maharashtra, 73% kept their date.

How many projects has D. S. Kulkarni Developers Limited registered with MahaRERA?

6 projects under 6 MahaRERA registrations; 0 completed on MahaRERA.

Does D. S. Kulkarni Developers Limited have MahaRERA regulatory cases?

6 regulatory cases name its registrations, including an insolvency (NCLT) case.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology