D. S. Kulkarni Developers Limited
Deedo IDDD-RGH8Of 6 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 73 mo late.
Delivery record
6 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Listed as an NCLT insolvency project | Dsk MadhukoshListed as NCLT project: DSK MADHUKOSH | Not on record |
| Listed as an NCLT insolvency project | Dsk Gold LeafListed as NCLT project: DSK GOLD LEAF | Not on record |
| Listed as an NCLT insolvency project | Dsk MayurbanListed as NCLT project: DSK MAYURBAN | Not on record |
| Listed as an NCLT insolvency project | Dsk NandanvanListed as NCLT project: DSK NANDANVAN | Not on record |
| Listed as an NCLT insolvency project | Dsk AnandghanListed as NCLT project: DSK ANANDGHAN | Not on record |
| Listed as an NCLT insolvency project | Waterfall ResidenceListed as NCLT project: WATERFALL RESIDENCE | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Dsk Gold LeafP52100004230 | Baner | Certificate Signed | 30 Oct 2020 | 30 Oct 2020 | +73 mo* |
| Dsk MayurbanP52100004304 | Pirangut | Certificate Signed | 30 Oct 2020 | 30 Oct 2020 | +73 mo* |
| Dsk AnandghanP52100005158 | Dhayari | Certificate Signed | 30 Apr 2022 | 30 Apr 2022 | +55 mo* |
| Dsk NandanvanP52100005572 | Pirangut | Certificate Signed | 30 Oct 2020 | 30 Oct 2020 | +73 mo* |
| Waterfall ResidenceP52100007164 | Haveli | Certificate Signed | 30 Oct 2022 | 30 Oct 2022 | +49 mo* |
| Dsk MadhukoshP51800009465 | Kurla | Certificate Signed | 30 Apr 2019 | 30 Apr 2019 | +91 mo* |
D. S. Kulkarni Developers Limited, in questions
Does D. S. Kulkarni Developers Limited finish projects on time?
Of 6 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 73 mo late. Across Maharashtra, 73% kept their date.
How many projects has D. S. Kulkarni Developers Limited registered with MahaRERA?
6 projects under 6 MahaRERA registrations; 0 completed on MahaRERA.
Does D. S. Kulkarni Developers Limited have MahaRERA regulatory cases?
6 regulatory cases name its registrations, including an insolvency (NCLT) case.