D.G.Land Developers Private Limited
Company or firm · 15 projects · 15 MahaRERA registrations
Also appears as D G LAND DEVELOPERS PRIVATE LIMITED · D.G. LAND DEVELOPERS PRIVATE LIMITED · D.G.LAND DEVELOPERS PVT LTD
Projects1515 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date46%5 of 11 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 6 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sheetal Om Jay AradhanaP51800000446 | Borivali | 2017 | Not reported | 31 Dec 2018 | 31 Mar 2021 | +27 months |
| Sheetal Vaibhav KutirP51800002084 | Borivali | 2017 | Not reported | 1 Jul 2023 | 31 Dec 2025 | +29 months |
| Sheetal AnjaliP99000005155 | Vasaivirar City (M Corp) | 2017 | Not reported | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| Sheetal KundP51800005924 | Borivali | 2017 | Not reported | 1 Jul 2023 | — | On date |
| Sheetal KrupaP51800006581 | Borivali | 2017 | Not reported | 31 Dec 2018 | 28 Jun 2024 | +66 months |
| Sheetal SejalP51800009516 | Mumbai | 2017 | Not reported | 1 Jul 2023 | — | On date |
| Sheetal JyotP99000010192 | Vasaivirar City (M Corp) | 2017 | Not reported | 1 Jul 2023 | — | On date |
| Sheetal DeepP99000010407 | Vasai Virar City (M Corp) | 2017 | Not reported | 31 Dec 2018 | 31 Dec 2023 | +60 months |
| Sheetal GrandeurP51800022875 | Andheri | 2019 | Not reported | 1 Oct 2023 | 31 Dec 2025 | +26 months |
| Sheetal DharmarajP51800027915 | Borivali | 2021 | Not reported | 13 Apr 2024 | — | On date |
| Sheetal TrimurtiP51800028316 | Borivali | 2021 | Not reported | 1 Dec 2023 | — | On date |
| Sheetal Usha And NishaP51800045746 | Borivali | 2022 | Not reported | 29 Apr 2027 | — | On date |
| Sheetal MeghdootP51800048997 | Borivali | 2023 | Not reported | 31 Dec 2026 | — | On date |
| Sheetal LennieP51800049785 | Oshiwara | 2023 | Not reported | 31 Dec 2026 | — | On date |
| Sheetal ElaraPM1180002600875 | Oshiwara | 2026 | Not reported | 31 Dec 2030 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 11 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 66 months, for Sheetal Krupa (P51800006581).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 4 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology