Choudhary Bhaishree Landmarks LLP
Deedo IDDD-G0GCOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 7 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Villo 67P51500024894 | Itkheda | Active | 30 Mar 2026 | — | +7 mo* |
Choudhary Bhaishree Landmarks LLP, in questions
Does Choudhary Bhaishree Landmarks LLP finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 7 mo late. Across Maharashtra, 73% kept their date.
How many projects has Choudhary Bhaishree Landmarks LLP registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Choudhary Bhaishree Landmarks LLP have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.