Skip to content
Deedo home
Menu

Cci Projects Private Limited

Company or firm · 8 projects · 8 MahaRERA registrations

8Projects8 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
WhitespringP51800002287Borivali2017Not reported31 Dec 2018—On date
WintergreenP51800003067Borivali2017Not reported31 Dec 201930 Dec 2021+24 months
The ArcadeP51800018662Borivali2018Not reported30 Dec 202130 Jun 2025+42 months
Rivali Park - SunburstP51800050351Magathane2023Not reported31 Aug 2028—On date
Rivali Park - StargazeP51800053578Magathane2023Not reported31 Oct 2029—On date
Rivali Park - MoonriseP51800055489Magathane2024Not reported30 Jun 2030—On date
Rivali Park - SkyleapPR1183032501382Magathane2025Not reported31 Jul 2032—On date
Rivali Park-SkyflowPR1184042502590Magathane2026Not reported31 Jul 2033—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • WhitespringOn date
  • Wintergreen+24 mo
  • The Arcade+42 mo
  • Rivali Park - SunburstOn date
  • Rivali Park - StargazeOn date
  • Rivali Park - MoonriseOn date
  • Rivali Park - SkyleapOn date
  • Rivali Park-SkyflowOn date

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 42 months, for The Arcade (P51800018662).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology