Cci Projects Private Limited
Company or firm · 8 projects · 8 MahaRERA registrations
8Projects8 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| WhitespringP51800002287 | Borivali | 2017 | Not reported | 31 Dec 2018 | — | On date |
| WintergreenP51800003067 | Borivali | 2017 | Not reported | 31 Dec 2019 | 30 Dec 2021 | +24 months |
| The ArcadeP51800018662 | Borivali | 2018 | Not reported | 30 Dec 2021 | 30 Jun 2025 | +42 months |
| Rivali Park - SunburstP51800050351 | Magathane | 2023 | Not reported | 31 Aug 2028 | — | On date |
| Rivali Park - StargazeP51800053578 | Magathane | 2023 | Not reported | 31 Oct 2029 | — | On date |
| Rivali Park - MoonriseP51800055489 | Magathane | 2024 | Not reported | 30 Jun 2030 | — | On date |
| Rivali Park - SkyleapPR1183032501382 | Magathane | 2025 | Not reported | 31 Jul 2032 | — | On date |
| Rivali Park-SkyflowPR1184042502590 | Magathane | 2026 | Not reported | 31 Jul 2033 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 42 months, for The Arcade (P51800018662).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology