Bramha Constructions

Deedo IDDD-H9YN

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 6 mo late.

Projects23 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay6 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Kailash ComplexP52000054450MamdapurCertificate Signed31 Mar 202631 Jul 2026+8 mo*
Kailash ComplexP52000055271MamdapurCertificate Signed31 Mar 202731 Jul 2027+4 mo
Kailash Complex Phase 3PR1272022602734MamdapurNot on record31 Dec 2031—On date

Bramha Constructions, in questions

Does Bramha Constructions finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 6 mo late. Across Maharashtra, 73% kept their date.

How many projects has Bramha Constructions registered with MahaRERA?

2 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.

Does Bramha Constructions have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology