Deedo IDDD-H9YNOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 6 mo late.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Kailash ComplexP52000054450 | Mamdapur | Certificate Signed | 31 Mar 2026 | 31 Jul 2026 | +8 mo* |
| Kailash ComplexP52000055271 | Mamdapur | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
| Kailash Complex Phase 3PR1272022602734 | Mamdapur | Not on record | 31 Dec 2031 | — | On date |
Bramha Constructions, in questions
Does Bramha Constructions finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 6 mo late. Across Maharashtra, 73% kept their date.
How many projects has Bramha Constructions registered with MahaRERA?
2 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Bramha Constructions have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.