Bombay Slum Redevelopment Corporation Pvt. Ltd
Deedo IDDD-YHYEOf 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 20 mo late.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| loginP51800006953 | Borivali | Certificate Signed | 30 Sep 2022 | 30 Sep 2023 | +12 mo |
| Shivshakti Nagar CHS C and D WingP51800028325 | Borivali | Certificate Signed | 31 Jul 2024 | 31 Jul 2024 | +28 mo* |
| Adarsh Nagar SRA CHS Ltd.P51800028687 | Borivali | Certificate Signed | 30 Mar 2023 | 30 Mar 2023 | On date |
Bombay Slum Redevelopment Corporation Pvt. Ltd, in questions
Does Bombay Slum Redevelopment Corporation Pvt. Ltd finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 20 mo late. Across Maharashtra, 73% kept their date.
How many projects has Bombay Slum Redevelopment Corporation Pvt. Ltd registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.
Does Bombay Slum Redevelopment Corporation Pvt. Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.