Bombay Construction & Infraprojects Pvt Ltd

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+27 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sahil ExoticaP51800003978Andheri2017Not reported30 Jun 201931 Dec 2023+54 months
99 Silver OaksP51700076739Ulawe2024Not reported31 Dec 2033—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sahil Exotica+54 mo
  • 99 Silver OaksOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 54 months, for Sahil Exotica (P51800003978).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology