Bombay Construction & Infraprojects Pvt Ltd

Deedo IDDD-Y1TZ

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 29 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay29 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sahil ExoticaP51800003978AndheriCertificate Signed30 Jun 201931 Dec 2023+54 mo
99 Silver OaksP51700076739UlaweCertificate Signed31 Dec 203330 Apr 2034+4 mo

Bombay Construction & Infraprojects Pvt Ltd, in questions

Does Bombay Construction & Infraprojects Pvt Ltd finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 29 mo late. Across Maharashtra, 73% kept their date.

How many projects has Bombay Construction & Infraprojects Pvt Ltd registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Bombay Construction & Infraprojects Pvt Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology