Bhuvi Landmarks Llp

Of 10 registrations whose promised date has arrived, 7 were never extended past it (70%).

Projects910 RERA registrations
Kept RERA date70%
Median delayNonewhen extended
Completed3as reported on MahaRERA
Regulatory cases1no insolvency
Bhuvi Landmarks Llp developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

3 registrations of 10 moved past the RERA date

Months late against the original RERA promise, per registration

10 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
complaintBhuvi MadhubanComplaint CC12604505Not on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Bhuvi MadhurbanP51500002962BalapurCertificate Signed31 Dec 201831 Dec 2019+12 mo
Bhuvi Vrundavan - 1P51500003772KubhephalCompleted31 Mar 2018—On date
KrishnabanP51400006388Jalna (M Cl)Completed31 Dec 201831 Dec 2019+12 mo
KrishnabanP51400011318Jalna (M Cl)Completed31 Mar 201930 Sep 2020+18 mo
Bhuvi GharkulP51500014339Aurangabad (M Corp.)Certificate Signed30 Dec 202130 Dec 2021On date
Bhuvi VishwabanP51500020149HirapurCertificate Signed30 Mar 202330 Mar 2023On date
Bhuvi MadhubanP51500020977HirapurLapsed30 May 2023—On date
Bhuvi Madhurban Phase-2P51500021822BalapurCertificate Signed31 Jul 202431 Jul 2024On date
Bhuvi Vishwaban Phase-2P51500022135HirapurCertificate Signed30 Dec 202430 Dec 2024On date
Shubh Labh HeightsP51500026771Aurangabad (M Corp.)Certificate Signed30 Apr 202630 Apr 2026On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology