Skip to content
Deedo home
Menu

Bhuvi Madhuban

Lapsed

Hirapur, Aurangabad 431001 |Promoter: Bhuvi Landmarks LLP

Residential / Group HousingRERAP51500020977
27 May 2019Registered with MahaRERA
30 May 2023Promised completion
5Buildings
11Units registered
1MahaRERA listings and orders

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Lapsed
Buildings
5
Unit types
R h no 1, R h no 5, R h no 6, R h no 711 units in all
Land area for this project
1,085 sq m (11,680 sq ft)
Permissible built-up area
501 sq m (5,393 sq ft)
Sanctioned built-up area
501 sq m (5,393 sq ft)
Address
Plot No. 21 Gut No. 37, Aurangabad, Jalna Road AurangabadPIN 431001
Designated bank account
Axis Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.66940, 76.04270
Bhuvi Madhuban is at latitude 20.66940, longitude 76.04270.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 May 2023

The latest completion date on record passed 3 years and 5 months ago.

Registered
27 May 2019
Promised
30 May 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5150002097727 May 201930 May 2023—Bhuvi Landmarks LLPProject page

5 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Madhuban——
R H No 1 To 414
R H No 531
R H No 631
R H No 7 To 1115

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

11 units registered

R h no 1 · 4 unitsR h no 5 · 1 unitR h no 6 · 1 unitR h no 7 · 5 units
BuildingTypeCarpet areaUnits
R H No 1 To 4R h no 134.61 sq m · 373 sq ft4
R H No 5R h no 563.7 sq m · 686 sq ft1
R H No 6R h no 667.9 sq m · 731 sq ft1
R H No 7 To 11R h no 737.84 sq m · 407 sq ft5

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
R H No 1 To 4Closed/Covered00000
R H No 1 To 4Open Space00000
R H No 5Closed/Covered00001
R H No 5Open Space00000
R H No 6Closed/Covered00001
R H No 6Open Space00000
R H No 7 To 11Closed/Covered00000
R H No 7 To 11Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

R H No 1 To 4

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

R H No 5

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

R H No 6

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

R H No 7 To 11

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsAS PER DRAWING100%
  • Water SupplyTHROUGH BOREWELL100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)NO STP100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingAS PER DRAWING100%
  • Street LightingAS PER DRAWING100%
Show all 16 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAS PER DRAWING100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationAS PER DRAWING100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable
  • Compound Wall Entrance GateAS PER DRAWING100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

32 documents held by Deedo, 37 filings listed on MahaRERA's project page

Title report

Building plan

Form B

Encumbrance details

Form 2A

Form 1 (7)

Show all 69 documentsShow fewer documents

Form 1 (7)

Form 2 (6)

Form 5 (4)

Registration certificate

Commencement certificate

Other (6)

Layout plan

Allotment letter

Document library

  • Declaration in FORM BForm B.pdf · uploaded 16 May 2019View
  • Copy of the legal title reportSearch Report.pdf · uploaded 16 May 2019View
  • Copy of Layout Approval (in case of layout)Final Layout.pdf · uploaded 16 May 2019View
  • Building Plan Approval (IOD)Building Permission.pdf · uploaded 16 May 2019View
  • Commencement Certificates / NA Order for plotted developmentcommencement Certificate.pdf · uploaded 16 May 2019View
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 16 May 2019View
  • Details of encumbrancesEncumbrance Cetificate.pdf · uploaded 17 May 2019View
  • Form 2AHirapur Gut No 37 Engineer's Certificate_compressed.pdf · uploaded 23 Jul 2019View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate_compressed.pdf · uploaded 27 Dec 2019View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate_compressed.pdf · uploaded 27 Dec 2019View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Certificate Madhuban.pdf · uploaded 20 Aug 2020View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate Madhuban.pdf · uploaded 20 Aug 2020View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM Bhuvi Madhuban.pdf · uploaded 30 Jan 2021View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Madhuban.pdf · uploaded 20 May 2021View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Madhuban.pdf · uploaded 20 May 2021View
  • Declaration about Commencement CertificateDECLARATION OF COMMENCEMENT.pdf · uploaded 9 Feb 2022View
  • Declaration about Commencement CertificateDECLARATION OF COMMENCEMENT.pdf · uploaded 9 Feb 2022View
  • Disclosure of sold/ booked inventorySOLD UNSOLD JUN-21.pdf · uploaded 9 Feb 2022View
  • Disclosure of sold/ booked inventorySOLD UNSOLD MAR-21.pdf · uploaded 9 Feb 2022View
  • Disclosure of sold/ booked inventorySOLD UNSOLD SEPT-21.pdf · uploaded 9 Feb 2022View
  • Disclosure of sold/ booked inventorySOLD UNSOLD DEC-21.pdf · uploaded 9 Feb 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)NA.pdf · uploaded 9 Feb 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)NA.pdf · uploaded 9 Feb 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)F-2 15-07-21_Compressed.pdf · uploaded 12 Feb 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)F-2SEPT-21_Compressed.pdf · uploaded 12 Feb 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)F-2 15-01-22_Compressed.pdf · uploaded 12 Feb 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)F-1 march 21.pdf · uploaded 22 Feb 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)F-1 June 21.pdf · uploaded 22 Feb 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)F-1 sep 21.pdf · uploaded 22 Feb 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)F-1 DEC 21.pdf · uploaded 22 Feb 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)From5_2021_Madhuban.pdf · uploaded 12 Mar 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form5_2122_Madhuban.pdf · uploaded 31 Jan 2023View

Promoter documents

  • Declaration Form BForm B.pdf · uploaded 16 May 2019View
  • Legal Title reportSearch Report.pdf · uploaded 16 May 2019View

Technical documents

  • Building Plan ApprovalBuilding Permission.pdfView
  • Layout ApprovalFinal Layout.pdfView

Proforma allotment letter

  • Proforma allotment letterAllotment Letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Hirapur, Aurangabad taluka

Survey, CTS, gat or plot numbers

PLOT NO. 21 GUT NO. 37

As published on MahaRERA's project page

PLOT NO. 21 GUT NO. 37

Boundaries

North
12 Meter Wide Road
South
Land Of Gut No 36
East
Land Of Gut No 41
West
Open Space And 9 Meter Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSameer Ausekar—
Chartered accountantPravin S Mundada—
OtherAnil Malani—
OtherShaikh Saleem Shaikh Ameen—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · MahaRERA regulatory lists and ordersData through is when MahaRERA's project page was last read.Methodology