Deedo IDDD-KP4YOf 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 8 mo late.
Delivery record
4 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Bhumi SilveriioP52100005434 | Chikhali | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Bhumi PrideP52100004657 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Bhumi Silveriio Phase 2P52100025555 | Chikhali | Certificate Signed | 30 Jun 2023 | 31 Dec 2023 | +41 mo* |
| Bhumi SilveriioP52100051295 | Chikhali | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Bhumi Silveriio - Phase 4PR1263032500910 | Chikhali | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
Bhumi Shelters (India) Pvt Ltd, in questions
Does Bhumi Shelters (India) Pvt Ltd finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has Bhumi Shelters (India) Pvt Ltd registered with MahaRERA?
4 projects under 5 MahaRERA registrations; 2 completed on MahaRERA.
Does Bhumi Shelters (India) Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.