Company or firm · first RERA registration 2018

Bhairavnath Developers

Deedo IDDD-T66Z

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 64 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay64 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shivsmruti ResidencyP52600014884Barshi (M Cl)Certificate Signed5 Jul 20215 Jul 2021+64 mo*

Bhairavnath Developers, in questions

Does Bhairavnath Developers finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 64 mo late. Across Maharashtra, 73% kept their date.

How many projects has Bhairavnath Developers registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Bhairavnath Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology