Deedo IDDD-0G25Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 35 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Terra GreensP52100011686 | Sangavade | Certificate Signed | 30 Dec 2023 | 29 Dec 2024 | +35 mo* |
| Terra GreensP52100048263 | Sangavade | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
Bhagwati Group, in questions
Does Bhagwati Group finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 35 mo late. Across Maharashtra, 73% kept their date.
How many projects has Bhagwati Group registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Bhagwati Group have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.