Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 33 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay33 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Indrayani Sankalp-MPMCP52100007861LohgaonCertificate Signed6 Feb 20245 Feb 2025+33 mo*

Bebanco Developers Ltd, in questions

Does Bebanco Developers Ltd finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 33 mo late. Across Maharashtra, 73% kept their date.

How many projects has Bebanco Developers Ltd registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Bebanco Developers Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.