B.Kalyanji Realty
Company or firm · 6 projects · 6 MahaRERA registrations
6Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
83%Kept RERA date5 of 6 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Govind SmrutiP52000002247 | Khopoli | 2017 | Certificate Signed | 25 Jul 2019 | 25 Jul 2019 | On date |
| The RhythmP52000020995 | Khopoli | 2019 | Certificate Signed | 15 May 2024 | 15 May 2024 | On date |
| SuyogP52000026252 | Khopoli | 2020 | Certificate Signed | 15 Aug 2022 | 15 Aug 2022 | On date |
| Kalyanji AshrayaP52000028681 | Khopoli | 2021 | Certificate Signed | 31 Jul 2023 | 31 Jul 2023 | On date |
| Saffron TowerP52000031209 | Khopoli | 2021 | Certificate Signed | 15 Feb 2024 | 10 Feb 2025 | +12 months |
| Kalyanji CallistaP52000047874 | Khopoli | 2022 | Certificate Signed | 30 Apr 2025 | 30 Apr 2025 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Saffron Tower (P52000031209).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology