Avior Majestique Properties
Deedo IDDD-5TKHOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 11 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| VanalikaP52100001569 | Pirangut | Certificate Signed | 31 Mar 2019 | 30 Sep 2020 | +18 mo |
| Vanalika-Paradise- III -3bP52100016963 | Pirangut | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Vanalika - Paradise - Phase - III-3aP52100019038 | Pirangut | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
Avior Majestique Properties, in questions
Does Avior Majestique Properties finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.
How many projects has Avior Majestique Properties registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.
Does Avior Majestique Properties have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.