Company or firm · first RERA registration 2017

Atlas Infratech Pvt.Ltd

Deedo IDDD-8BNV

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 47 mo late.

Projects23 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay47 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Atlas RoyalP51900013134Ward AbcdCertificate Signed31 Dec 201831 Dec 2025+95 mo*
Atlas RoyalP51900015871Ward AbcdCertificate Signed30 Dec 202231 Dec 2025+47 mo*
Atlas Residency A and BP51900080731Ward GsouthCertificate Signed31 Dec 202830 Apr 2029+4 mo

Atlas Infratech Pvt.Ltd, in questions

Does Atlas Infratech Pvt.Ltd finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 47 mo late. Across Maharashtra, 73% kept their date.

How many projects has Atlas Infratech Pvt.Ltd registered with MahaRERA?

2 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.

Does Atlas Infratech Pvt.Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology