Atlas Infratech Pvt.Ltd
Deedo IDDD-8BNVOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 47 mo late.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Atlas RoyalP51900013134 | Ward Abcd | Certificate Signed | 31 Dec 2018 | 31 Dec 2025 | +95 mo* |
| Atlas RoyalP51900015871 | Ward Abcd | Certificate Signed | 30 Dec 2022 | 31 Dec 2025 | +47 mo* |
| Atlas Residency A and BP51900080731 | Ward Gsouth | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
Atlas Infratech Pvt.Ltd, in questions
Does Atlas Infratech Pvt.Ltd finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 47 mo late. Across Maharashtra, 73% kept their date.
How many projects has Atlas Infratech Pvt.Ltd registered with MahaRERA?
2 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Atlas Infratech Pvt.Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.