P51900080731

Atlas Residency A and B · Ward Gsouth, Mumbai City · Atlas Infratech Pvt.Ltd

Promised for 31 Dec 2028, extended to 30 Apr 2029, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2028 to 30 Apr 2029.

Documents 1

Registration certificate30 Jun 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P51900080731

Is Atlas Residency A and B delayed?

Its completion moved from 31 Dec 2028 to 30 Apr 2029; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51900080731. The completion date moved from 31 Dec 2028 to 30 Apr 2029.

Who is the promoter?

MahaRERA records Atlas Infratech Pvt.Ltd as the promoter of P51900080731.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51900080731.

Answers are generated from the record.

Data through23 Oct 2026, 02:23SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology