Company or firm · first RERA registration 2018
Asiad Housing And Property Development Services Pvt Ltd
Deedo IDDD-F6AROf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 53 mo late.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay53 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | AsiadRegulatory order: PROJECT NAME: ASIAD (Regulatory Case No. 39 of 2023) dated 18 August 2023. | 22 Aug 2023 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| AsiadP51800014772 | Kurla | Certificate Signed | 30 Jun 2022 | 31 Oct 2024 | +53 mo* |
Asiad Housing And Property Development Services Pvt Ltd, in questions
Does Asiad Housing And Property Development Services Pvt Ltd finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 53 mo late. Across Maharashtra, 73% kept their date.
How many projects has Asiad Housing And Property Development Services Pvt Ltd registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Asiad Housing And Property Development Services Pvt Ltd have MahaRERA regulatory cases?
1 regulatory case name its registrations.