Ashok Ramchandra Yamgekar
Deedo IDDD-47YPOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 54 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ayodhya Park Phase IP53000019325 | Gadhinglaj | Certificate Signed | 30 May 2022 | 30 May 2022 | +54 mo* |
Ashok Ramchandra Yamgekar, in questions
Does Ashok Ramchandra Yamgekar finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 54 mo late. Across Maharashtra, 73% kept their date.
How many projects has Ashok Ramchandra Yamgekar registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Ashok Ramchandra Yamgekar have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.