Ashiana Housing Limited
Deedo IDDD-9PRYOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.
Delivery record
6 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ashiana Malhar Phase I and Commercial BlockP52100046049 | Mulshi | Certificate Signed | 31 Oct 2026 | 31 Oct 2026 | +1 mo* |
| Ashiana AmodhP52100050979 | Varale | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
| Ashiana MalharP52100052593 | Marunji | Certificate Signed | 31 May 2027 | 30 Sep 2027 | +4 mo |
| NiwasP52100054148 | Marunji | Certificate Signed | 28 Jan 2029 | 28 May 2029 | +4 mo |
| Ashiana AmodhP52100056484 | Varale | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 mo |
| Ashiana MalharP52100076601 | Marunji | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 mo |
Ashiana Housing Limited, in questions
Does Ashiana Housing Limited finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Ashiana Housing Limited registered with MahaRERA?
4 projects under 6 MahaRERA registrations; 0 completed on MahaRERA.
Does Ashiana Housing Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.