Arun Pitamber Sheth

Individual promoter · 8 projects · 8 MahaRERA registrations

Projects88 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date75%3 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Anika EnclaveP52100001676Pune (M Corp.)2017Not reported31 Dec 2017—On date
Anika Laxmi NiwasP52100014468Gultekadi2017Not reported31 Jul 201930 Jan 2021+18 months
Anika ArcadeP52100018361Pisoli2018Not reported31 May 2019—On date
Anika RegaliaP52100019498Pune (M Corp.)2019Not reported30 Dec 2022—On date
Anika Piccadilly Phase 1P52100022784Punawale2019Not reported30 Dec 2026—On date
Anika Piccadilly Phase 2P52100049940Punawale2023Not reported31 Dec 2027—On date
Anika Piccadilly Phase 3P52100078875Punawale2025Not reported31 Dec 2028—On date
Anika Piccadilly Phase 4PR1261012601568Punawale2026Not reported31 Dec 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Anika EnclaveOn date
  • Anika Laxmi Niwas+18 mo
  • Anika ArcadeOn date
  • Anika RegaliaOn date
  • Anika Piccadilly Phase 1On date
  • Anika Piccadilly Phase 2On date
  • Anika Piccadilly Phase 3On date
  • Anika Piccadilly Phase 4On date

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Anika Laxmi Niwas (P52100014468).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology