Arun Pitamber Sheth
Individual promoter · 8 projects · 8 MahaRERA registrations
Projects88 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date75%3 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Anika EnclaveP52100001676 | Pune (M Corp.) | 2017 | Not reported | 31 Dec 2017 | — | On date |
| Anika Laxmi NiwasP52100014468 | Gultekadi | 2017 | Not reported | 31 Jul 2019 | 30 Jan 2021 | +18 months |
| Anika ArcadeP52100018361 | Pisoli | 2018 | Not reported | 31 May 2019 | — | On date |
| Anika RegaliaP52100019498 | Pune (M Corp.) | 2019 | Not reported | 30 Dec 2022 | — | On date |
| Anika Piccadilly Phase 1P52100022784 | Punawale | 2019 | Not reported | 30 Dec 2026 | — | On date |
| Anika Piccadilly Phase 2P52100049940 | Punawale | 2023 | Not reported | 31 Dec 2027 | — | On date |
| Anika Piccadilly Phase 3P52100078875 | Punawale | 2025 | Not reported | 31 Dec 2028 | — | On date |
| Anika Piccadilly Phase 4PR1261012601568 | Punawale | 2026 | Not reported | 31 Dec 2029 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Anika Laxmi Niwas (P52100014468).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology