Arihant Superstructures Limited
Deedo IDDD-F4B6Of 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Delivery record
11 of 15 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 15 registrations
15 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Arihant Adarsh Phase IRegulatory order: PROJECT NAME: ARIHANT ADARSH PHASE I (Regulatory Case No. 257 OF 2024) dated 04 Feb, 2025. | 4 Feb 2025 |
| complaint | Arihant AvantiComplaint CC12400723 | Not on record |
| complaint | Arihant AvantiComplaint SM12600280 | Not on record |
| complaint | Arihant AvantiComplaint CC12602896 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Arihant ArshiyaP52000002342 | Dahivali Tarf Boreti | Certificate Signed | 30 Mar 2019 | 29 Sep 2020 | +18 mo |
| Arihant ArshiyaP52000003422 | Dahivali Tarf Boreti | Certificate Signed | 30 Sep 2020 | 30 Sep 2020 | On date |
| Arihant AarohiP51700004679 | Thane | Certificate Signed | 30 Apr 2019 | 29 Oct 2020 | +18 mo |
| Arihant AarohiP51700015328 | Thane | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| 4AnaikaP52000022982 | Koyana Velhe | Certificate Signed | 30 Dec 2027 | 30 Dec 2027 | On date |
| Arihant Aakarshan Phase IP52000034793 | Ghot | Certificate Signed | 31 Mar 2030 | 31 Jul 2030 | +4 mo |
| Arihant Aaradhya Phase IP51700045430 | Bapgaon | Certificate Signed | 31 Mar 2029 | 31 Jul 2029 | +4 mo |
| Arihant Adarsh Phase IP52000045699 | Ghot | Certificate Signed | 31 Mar 2030 | 31 Dec 2032 | +33 mo |
| Arihant Aayan Phase IP51700049910 | Titwala | Certificate Signed | 28 Dec 2030 | 28 Apr 2031 | +4 mo |
| Arihant Aaradhya Phase IIP51700049981 | Bapgaon | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
| Arihant ArshiyaP52000056037 | Dahivali Tarf Boreti | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
| Arihant 7anaikaP52000056420 | Koyana Velhe | Certificate Signed | 31 Dec 2031 | 30 Apr 2032 | +4 mo |
| World Villas Phase 1P52000076635 | Bhilvale | Certificate Signed | 31 Mar 2030 | 31 Jul 2030 | +4 mo |
| Arihant AvantiP51700077377 | Thane (M Corp.) | Active | 31 Dec 2031 | — | On date |
| Arihant AvantiP51700078840 | Thane (M Corp.) | Certificate Signed | 31 Dec 2031 | 30 Apr 2032 | +4 mo |
Show all 15 registrationsShow fewer
Arihant Superstructures Limited, in questions
Does Arihant Superstructures Limited finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 2 kept it (50%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Arihant Superstructures Limited registered with MahaRERA?
11 projects under 15 MahaRERA registrations; 5 completed on MahaRERA.
Does Arihant Superstructures Limited have MahaRERA regulatory cases?
4 regulatory cases name its registrations.