Arhum Erectors Private Limited
Company or firm · 5 projects · 5 MahaRERA registrations
Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date80%4 of 5 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| VTP Beaumonde Nation R2 Tower6P52100007942 | Manjari Kh | 2017 | Not reported | 16 Aug 2024 | 15 Aug 2025 | +12 months |
| VTP Beaumonde Building T3P52100022781 | Manjari Kh | 2019 | Not reported | 30 Jun 2025 | — | On date |
| VTP Cygnus Building T11P52100022783 | Manjari Kh | 2019 | Not reported | 30 Jun 2025 | — | On date |
| VTP Cygnus BuildingT12 and CommercialP52100023473 | Manjari | 2019 | Not reported | 30 Jun 2025 | — | On date |
| VTP Cygnus Building T10P52100024551 | Manjari Kh | 2020 | Not reported | 30 Jun 2025 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for VTP Beaumonde Nation R2 Tower6 (P52100007942).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology