Company or firm · first RERA registration 2023

Ardhya Universal LLP

Deedo IDDD-C4TP

None of 2 registrations has reached its promised completion date yet.

Projects22 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Malad Amar Co-Operative Housing Society Ltd.P51800052335MaladCertificate Signed31 Dec 202630 Apr 2027+4 mo
Ardhya AuraPR1180002601753MalvaniCertificate Signed4 Jun 20294 Jun 2029On date

Ardhya Universal LLP, in questions

Does Ardhya Universal LLP finish projects on time?

None of its 2 MahaRERA registrations has reached its promised completion date yet.

How many projects has Ardhya Universal LLP registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Ardhya Universal LLP have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.