Deedo IDDD-944KOf 7 registrations whose promised date has arrived, 7 kept it (100%).
Delivery record
1 of 8 registrations with dates moved or missed their RERA date · months late against the original promise
8 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Patels ElysiumP51700005803 | Ambarnath(M Cl) | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Patels ElysiumP51700006142 | Ambarnath(M Cl) | Certificate Signed | 30 Oct 2023 | 30 Oct 2023 | On date |
| Patels ElysiumP51700008491 | Ambarnath(M Cl) | Certificate Signed | 30 Oct 2023 | 30 Oct 2023 | On date |
| Patels ElysiumP51700009032 | Ambarnath(M Cl) | Completed | 30 Dec 2023 | — | On date |
| Patels ElysiumP51700009543 | Ambarnath(M Cl) | Certificate Signed | 31 Oct 2019 | 31 Oct 2019 | On date |
| Patels ElysiumP51700010280 | Ambarnath(M Cl) | Certificate Signed | 30 Oct 2023 | 30 Oct 2023 | On date |
| Patels ElysiumP51700010318 | Ambarnath(M Cl) | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Patels ElaraPM1330002501154 | Ambarnath(M Cl) | Certificate Signed | 1 Nov 2028 | 1 Mar 2029 | +4 mo |
Apace Realty, in questions
Does Apace Realty finish projects on time?
Of 7 MahaRERA registrations whose promised completion date has arrived, 7 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Apace Realty registered with MahaRERA?
2 projects under 8 MahaRERA registrations; 7 completed on MahaRERA.
Does Apace Realty have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.